Concrete batching
Your current location: 首 页 > Chongqing simple mixing station

Chongqing Xiannu mountain mixing plant vision

2020-05-08 14:53:39
Chongqing Xiannu mountain mixing plant vision
Detailed introduction:

Mixing plant equipment

Mixing plant equipment

1. Road speed: 24 km/ h, taking the round-trip distance of 24 km as an example。

2、Concrete mixing transport truckLoading time: HZS120 machine 1/6 hour/car, HZS90 machine 7/30 hour。

3, concrete mixing transport truck unloading time: 5 minutes。

4, every completed 1 car concrete transport: HZS120 machine needs 1.25 hours. The HZS90 takes 1.32小时。

5, the number of vehicles transported within 6 hours: HZS120 machine 6×1/1.25≈5(car), HZS90 machine 6×1/1.32≈4(车)。

6. Beam pouring concrete 320 m3 is completed within 6 hours, and the number of transport vehicles required is 320×1/6.5≈50(车)。

7, the equipment of concrete mixing transport vehicles should consider that due to the road transportation should leave a certain empty tank rate。HZS120agitatorStation, the host capacity is 2m3, should be equipped with 9 m3 concrete mixing transport truck, in order to easily load 4 trays of materials。The transport distance is about 12KM, the beam pouring concrete is 320 m3 within 6 hours, and it is suitable to be equipped with 10~11 concrete mixing transport vehicles。

8, HZS90 mixer station host capacity is 1.5 m3, should be equipped with 8 m3 concrete mixing transport truck, in order to easily load 5 trays of materials。HZS90+HZS120 mixer station should be equipped with 8m3 concrete mixing transport truck to easily load 4 trays of materials。The transport distance is 12KM, the beam pouring concrete is 320 m3 within 6 hours, and 13 to 14 concrete mixing trucks should be equipped。